Kupe

Kupe

Kupe In October 2012 Steamtech carried out the successful degassing and decontamination of 18 vessels on the Kupe site for Origin Energy. A total of 15 staff worked on a 24 hour shift to complete the project. Our new 200HP unit that was commissioned that same month...
Maui A

Maui A

Maui In February 2013 Steamtech carried out the degassing and decontamination of the Depropaniser and associated vessels. Our 200HP was used and the section of the plant was steamed as a package, in one end and out the other. One of a number of successful projects...
Pohokura

Pohokura

Pohokura   In January 2012 Steamtech carried out the degassing and decontamination of a number of vessels and columns including the Glycol skid. Our 150HP unit was used on this project enabling the column, glycol skid and associated vessels to all be steamed at...